We are finally getting closer to the finish line, Alhamdullilah selection of the prayer rug was made and ordered. Here is a picture of the selected - Red Border Elegance design.
The contractors were able to start the laying of 4" water pipeline for the fire sprinkler system. Here are few pictures of the exterior pipeline work in progress.
We are catching up on the updates of the construction work related to the New Masjid, in January 2020 the building work restarted after a prolong delay. Here are the pictures with new doors and windows that were installed.
Alhamdullilah, we have reached an important milestone in completion of the site work. This work involved: parking lot, elevator, steps, storm water drain pit, lights, etc. Here are pictures of the parking lot lights.
Here are few pictures of the finished building elevation work, with the final color selections. The parking lot striping was also completed. Presently, fire sprinkler system work in progress and is expected to finish in the month of August. Our contractors have done a great job on the building elevation and coloring. Alhamdullilah! we are all excited about the updated proposed elevation of the Masjid Building, here is a sneak peak of what's being worked on and sharing the design rendering of the same. May Allah help us in getting the proposed elevation approved by the Township and to complete the Masjid building as early as possible. Please remember in your prayers and financially support the project. Without the community support all this work in the cause of Allah would not be possible. Jazak Allah Khairan.
The interior work is progressing: framing, rough-in electric and HVAC work is completed. Next would be rough-in inspections and start of the plumbing work.
|
AuthorUpdates are provided by MCSC Board Members in order to keep the Community informed of the latest developments related to New Masjid and related events. Archives